top of page
Project:
Disney's Winnie-the-Pooh movie .
​
Work:
Several elements for a large location build (Int London Train Station), including a structural victorian bridge.
Communicating with other departments to maintain the site plan. Four weeks on location in Dover helping with the install and shoot.
​
The bridge was the largest built element at this location.
It required careful liaison between the steel suppliers, the structural engineer and Construction, and incorporated almost 10,000 resin rivet heads.
​
Media:
3D and 2D VectorWorks
​
Production Designer: Jennifer Williams
Supervising Art Director:  Stuart Kearns
bottom of page